RAPID CITY - The construction season is in full swing, and local projects are right on track, despite a snowy spring.

One such project, at the intersection of St. Patrick and Cambell streets, is progressing nicely and will be on schedule for its Oct. 14 completion date, South Dakota Department of Transportation project engineer John Gerlach said.

Traffic flow is currently limited in that area to two lanes on the east half of Cambell Street and part of E. St. Patrick Street. But he said the area should be more accessible soon.

“We're hoping to open up the intersection a little more Saturday,” he said, referring to Saturday, April 15. “It will still be a four-way stop, but hopefully by a week after Saturday we'll have the signals in place.”

At that point, E. St. Patrick Street will be back in regular operation, if things go as planned.

“East St. Patrick Street should be back to normal by a week from Saturday if all the materials get supplied from the contractor,” he said.

Once finished, East St. Patrick Street will include a right turn lane for northbound Cambell Street traffic, so that cars turning right onto Cambell can get through the intersection more quickly, he said.

Another main project is to widen Cambell Street.

“We're making it a five-lane road, two lanes northbound, two lanes southbound then a middle turn lane, with an exception through the bridge. The bridge will still be four lanes,” he said.

Two-lane traffic on Cambell Street will switch areas this summer while crews finish the other side of the road.

“We're working on the east half of Cambell Street, which is scheduled to be paved back by mid-July,” he said. “At that time, we'll switch traffic and put them head-to-head on the new pavement and tear up the west half of Cambell Street and start construction on that.”

Gerlach also emphasized that area residents need to be patient during construction.

“People need to stay alert and pay attention,” he said. “At times, traffic will be stopped due to construction activities.”

Meanwhile, work at the Interstate 90 Exit 32 interchange near Sturgis, which has been ongoing since 2004, will be done in time for the Sturgis motorcycle rally this year, Palmer said. He said the rally is the absolute deadline for that project.

“We have to be opened back up for the rally,” he said.

Palmer said the recent snow set his project back “three or four days” but that it remains on schedule and should be done by the rally deadline.

The Exit 32 project includes work on the Exit 32 interchange, Junction Avenue itself and bridges on Sales Ring Road and Junction Avenue, Palmer said. Junction Avenue will also be extended to Vanocker Canyon Road. In addition, work is being done on the eastbound lanes of Interstate 90.

Those lanes are being detoured now but will be fully functional for the rally, as will the Exit 32 interchange, according to the DOT.

Contact Ryan Woodard at 394-8412 or ryan.woodard@rapidcityjournal.com

Rapid Reply

Send us your Rapid Reply

(optional)
   
The preceeding are comments from the readers. In no way do they represent the views of the Rapid City Journal or Lee Enterprises.

The opinions above are from readers of rapidcityjournal.com and in no way represent the views of the Rapid City Journal or Lee Enterprises.

Rapidcityjournal.com provides this community forum for readers to exchange ideas and opinions on the news of the day. Passionate views, pointed criticism and critical thinking are welcome. Name-calling, crude language and personal abuse are not welcome. Moderators will monitor comments with an eye toward maintaining a high level of civility in this forum. Our comment policy explains the rules of the road for registered commenters.

If you don't see your comment, perhaps...

  • you called someone an idiot, a racist, a dope, a moron, etc. Please, no name-calling or profanity (or veiled profanity -- #$%^&*).
  • you rambled, failed to stay on topic or exhibited troll-like behavior intended to hijack the discussion at hand.
  • YOU SHOUTED YOUR COMMENT IN ALL CAPS. This is hard to read and annoys readers.
  • you named a business or identified a business in a way good or bad. Contact the business directly with your customer service concerns or your praise – they’ll likely appreciate your feedback.
  • you believe the newspaper's coverage is unfair. It would be better to write Jerry Steinley at jerry.steinley@rapidcityjournal.com or call him at 394-8427. This is a forum for community discussion, not for media criticism. We'd rather address your concerns directly.
  • you included an e-mail address or phone number, pretended to be someone you aren't or offered a comment that makes no sense.
  • you accused someone of a crime or assigned guilt or punishment to someone suspected of a crime.
  • your comment is in really poor taste.

Terms of Use | Privacy Policy

Construction on Cambell Street at E. St. Patrick Street has funneled traffic into two lanes. Signs warn of 10-minute delays during rush hour. The road work is expected to last through October, although the DOT hopes to fully open up E. St. Patrick Street within a week. (Steve McEnroe/Journal staff)

Top Jobs

Featured Dealers

Newspaper Ads

RCJ Extras

Advertisement